HomeMy WebLinkAbout2009-4-7536ORDINANCE NO. 2009-4-7536
AN ORDINANCE ACCEPTING THE BID FOR THE CITY OF PADUCAH' S
2009-2010 CONCRETE PROGRAM, AND AUTHORIZING THE MAYOR TO EXECUTE A
CONTRACT FOR SAME
BE IT ORDAINED BY THE CITY OF PADUCAH, KENTUCKY:
SECTION 1. That the City accepts the bid of Wilkins Construction Company, Inc.,
for the 2009-2010 concrete program, with the option of a one-year extension, said bid being in
substantial compliance with the bid specifications, and as contained in the bid of Wilkins
Construction Company, Inc., of March 25, 2009, for the following unit prices and hourly rates:
CONCRETE REMOVAL AND REPLACEMENT
ITEM
NO
DESCRIPTION
UNIT
UNIT BID
PRICE
1
Curb & Gutter (Remove & Construct)
L.F.
$38.00
2
Curb & Gutter (New Construction)
L.F.
$22.00
3
Concrete Sidewalk (Remove & Construct)
S.Y.
$56.00
4
Concrete Sidewalk (New Construction)
S.Y.
$42.00
5
Concrete Handicap Ramp
S.Y.
$60.00
6
Concrete Entrance Pavement — 6" (Residential)
S.Y.
$60.00
7
Concrete Entrance Pavement — 8" (Commercial)
S.Y.
$65.00
8
Concrete Entrance Pavement — 6" M -Mix
S.Y.
$69.00
9
Concrete Entrance Pavement- 8" M -Mix
S.Y.
$74.00
10
Granite Curb Reset with new Concrete Gutter
L.F.
$44.00
11
Gutter Replacement — Granite Curb in Place
L.F.
$37.00
12
Concrete Barrier Median
S.Y.
$60.00
13
Concrete Header Curb —12"
L.F.
$28.00
14
Concrete Header Curb —18"
L.F.
$35.00
15
Non -Reinforced Concrete 8"
S.Y.
$58.00
16
Inlet Repair (Existing)
Each
$780.00
17
Reinforced Concrete New Construction —Class A
C.Y.
$980.00
18
Deep Saw Cut
L.F.
$5.50
19
Perforated Pipe — 4"
L.F.
$11.50
EXCAVATION WORK
ITEM
NO
DESCRIPTION
UNIT
UNIT BID
PRICE
1
Trackhoe
HR
$116.00
2
Backhoe
HR
$88.00
3
Compactor/Roller
HR
$68.00
4
Dump Truck
HR
$88.00
5
Backhoe with Breaker
HR
$91.00
6
Laborer
HR
$52.00
SECTION 2. The Mayor is hereby authorized and directed to execute a contract
with Wilkins Construction Company, Inc., for concrete work at the unit prices and hourly rates as
authorized in Section 1 above, according to the specifications, bid proposal and contract documents
heretofore approved and incorporated in the bid of March 25, 2009.
SECTION 3. Expenditures for the City's concrete program shall be charged to
various accounts.
SECTION 4. The contract shall be binding upon the City and the Contractor, his
partners, successors, assigns and legal representatives for the 2009-2010 calendar year ending
December 31, 2010. Neither the City nor the Contractor shall have the right to assign, transfer, or
sublet their interests or obligations hereunder without consent of the other party. The term of the
contract shall be renewable for an additional one-year term, ending December 31, 2011, upon the
mutual agreement of both parties. The Board of Commissioners of the City of Paducah hereby
authorizes the City Engineer, in his sole discretion, to exercise this renewal option. This renewal
option shall be exercised by both parties executing and delivering the written One -Year Renewal
Agreement prior to the expiration of the original term of the contract. The City reserves the right to
have concrete work completed at the quoted prices until the One -Year Renewal Agreement has been
executed by the parties. However, in no case shall the Contractor be bound to complete the work at
these prices past December 31, 2010.
SECTION 5. This ordinance shall be read on two separate days and will become
effective upon summary publication pursuant to KRS Chapter 424.
ATTEST:
Tammara S. Brock, City Clerk
Introduced by the Board of Commissioners, April 14, 2009
Adopted by the Board of Commissioners, April 28, 2009
Recorded by Tammara S. Brock, City Clerk, April 28, 2009
Published by The Paducah Sun, May 6, 2009
\ord\eng\concrete program 2009 & 2010