HomeMy WebLinkAbout2013-10-8090ORDINANCE 2013-10-8090
AN ORDINANCE APPROVING CHANGE ORDER #2 WITH MAC
CONSTRUCTION & EXCAVATING, INC., FOR THE RIVERFRONT REDEVELOPMENT
PROJECT PHASE 1-A, PILES AND MASS FILL, AND AUTHORIZING THE MAYOR TO
EXECUTE SAID CHANGE ORDER
WHEREAS, the City approved Ordinance No. 2013-4-8029 to enter into an agreement
�. with MAC Construction & Excavating, Inc., in the amount of $4,490,600.00 for Riverfront
Redevelopment Project Phase 1-A, Piles and Mass Fill; and
WHEREAS, the City approved Change Order #1 approved by Ordinance No. 2013-8-
8062.to increase the contract amount by $16,800.00 to allow for the demolition of the Executive Inn
concrete slab for use as mass fill and to decrease the contract amount by $16,800.000 deducting 1,400
tons of Stone Fill at $12.00, therefore, an increase was not necessary to the total project cost of
$4,490,600.00; and
WHEREAS, all work associated with the Contract for Phase 1-A Project has been
completed; and
WHEREAS, to finalize payment for the project, Change Order #2 is requested in the
amount of $314,428.82, for the combination of the three items listed below the new total contract price
amount will be $4,805,028.82; and
1. Extension of the Gangway Piles $192,428.82
2. Temporary Shut -Down Barge Retainage $ 42,000.00
3. Orderly Shut-Down/Project Stabilization $ 80,000.00
Total of Change Order #2 $314,428.82
WHEREAS, in order to provide the additional expenses associated with Change Order
#2 the Finance Director is authorized and directed to transfer $50,000 from the Investment Fund to the
Riverfront Development Project account and reduce the transfer to the MAP Fund by $50,000.
BE IT ORDAINED BY THE CITY OF PADUCAH, KENTUCKY:
SECTION 1. The City of Paducah hereby approves Change Order No.2 with MAC
Construction & Excavating, Inc.in the amount of $314,428.82, therefore, increasing the total contract
price to $4,805,028.82 for the Riverfront Redevelopment Project Phase 1-A, Piles and Mass Fill.
SECTION 2. With the approval of Change Order No. 2 in Section 1 above, the Finance
Director is authorized and directed to transfer the required additional $50,000 from the Investment Fund
to the Riverfront Development Project account and reduce the transfer from the Investment Fund to the
MAP Fund by $50,000.
SECTION 3. The Mayor is hereby authorized to execute Change Order No. 2 approved
in Section 1 above.
SECTION 4. This ordinance shall be read on two separate days and will become
effective upon summary publication pursuant to KRS Chapter 424.
A TEST:
Tammara S. Sanderson, City Clerk
Introduced by the Board of Commissioners October 8, 2013
Adopted by the Board of Commissioners, October 15, 2013
Recorded by Tammara S. Sanderson, City Clerk, October 15, 2013
Published by The Paducah Sun, October 21, 2013