ORDINANCE NO. 94-2-JO%5
AN ORDINANCE AUTHORIZING THE MAYOR TO EXECUTE
CHANGE ORDER NO. 1 IN THE AMOUNT OF $18,935.47 AND CHANGE
ORDER NO. 2 IN AN AMOUNT UP TO $26,000.00 WITH VANGUARD
CONTRACTORS FOR CONSTRUCTION OF THE RIVERFRONT PLAZA, AND
AMENDING THE CONTRACT END DATE TO MARCH 30, 1994 FOR
THIS PROJECT
WHEREAS, the City entered into a contract with
Vanguard Contractors Inc. for construction of the Downtown
Riverfront Plaza; and
WHEREAS, Change Order No. 1 is required in order
to reduce construction material quantities, which decreases
the original contract price, and gives 28 additional days
for completion of contract; and
WHEREAS, Change Order No. 2 is required for the
installation of an enhanced design handrail and ADA approved
grabrail for the Plaza, for additional utility work, and to
extend the duration of the contract by up to 98 days, or
March 30, 1994.
BE IT ORDAINED BY THE CITY OF PADUCAH, KENTUCKY:
SECTION 1. The Mayor is hereby authorized and
directed to execute the following Change Orders with
Vanguard Contractors Inc. for construction of the Riverfront
I
Plaza:
Change Order No. 1 in the amount of $18,935.47 is
required to reduce the quantities of construction
materials, thereby decreasing the original
contract price and extending the contract
completion date by 28 days, necessitated by summer
flooding; and
Change Order No. 2 in an amount up to $26,000.00
is required for the installation of an enhanced
design handrail and ADA approved grabrail, for
additional utility work, and to extend the
contract completion date by an additional 98 days,
or March 30, 1994, necessitated by additional
inclement weather.
These Change Orders are attached hereto and incorporated by
reference as if fully set out herein.
SECTION 2. The original contract with Vanguard
Contracts Inc. is extended to March 30, 1994, for completion
of this project.
SECTION 3. The amount of the contract with
i
Vanguard Contractors Inc. is amended to $1,185.136.58.
SECTION 4. This expenditure shall be charged to
Account No. 42-88-20-466.
SECTION 5. Due to inclement weather which has
delayed construction since the implementation of this
393
contract, an emergency is hereby declared to exist and this
ordinance shall become effective immediately with one
reading.
Mayor
ATTEST:
City Clerk
Introduced and Adopted by the Board of Commissioners
February 15, 1994
Recorded by Lenita Smith, City Clerk, Februar 15, 1994
Published by The Paducah Sun J.-Z1� a1,19W