EXECUTE CHANGE ORDER NO. 2 IN THE AMOUNT OF $26,418.12 WITH CENTRAL
PAVING COMPANY OF PADUCAH FOR THE HILL TERRACE ROADWAY
IMPROVEMENT PROJECT
WHEREAS, the City approved Ordinance No. 95-7-5327 to enter into a contract
with Central Paving Company of Paducah for the Hill Terrace Roadway Improvement Project;
and
WHEREAS, Change Order No. 1 was required for an increase in the amount of
$72,795.09 for additional roadway construction; and
WHEREAS, Change Order No. 2 is required for an increase in the amount of
$26,418.12 for additional excavation and other required materials to complete this project for the
above referenced contract in the amount of $278,554.85, increasing the total contract price to
$304,972.97.
BE IT ORDAINED BY THE CITY OF PADUCAH, KENTUCKY:
SECTION 1. The Mayor is hereby authorized and directed to execute Change
Order No. 2 for an increase in the amount of $26,418.12 with Central Paving Company of
Paducah for additional excavation and other required materials to complete the Hill Terrace
Roadway Project, increasing the total cost to $304,972.97.
SECTION 2. This ordinance shall be read on two separate days and shall become
effective upon summary publication pursuant to KRS Chapter 424.
ATTEST:
Introduced by the Board of Commissioners December 5, 1995
Adopted by the Board of Commissioners December 12, 1995
Recorded by Lenita Smith, City Cler December 12, 1995
Published by The Paducah Sun. - /6, I9 9z-'
\winword\ordinanc\dees\cohill