HomeMy WebLinkAboutMO #3291MUNICIPAL ORDER NO. 3291
A MUNICIPAL ORDER ADOPTING CONTRACT MODIFICATION NO. 7 TO
THE CONSTRUCTION CONTRACT WITH A&K CONSTRUCTION,
REDUCING SAID CONTRACT BY $476,506, UPDATING THE CONTRACT
AMOUNT TO $50,460,285, AND AUTHORIZING THE MAYOR TO
EXECUTE ALL DOCUMENTS RELATED TO SAME
WHEREAS, on June 25, 2024, the Board of Commissioners approved a contract
with A&K Construction in the amount of $47,771,838.83 for the construction of the Paducah
Sports Park in partnership with the Fiscal Court and the McCracken County Sports Commission;
and
WHEREAS, at that time, construction of the championship field and entry plaza
was removed from the project; and
WHEREAS, on January 28, 2025, the Board of Commissioners approved Contract
Modification No. 1 with A&K Construction in the amount of $999,000 for the construction of the
championship field; and
WHEREAS, on August 12, 2025, the Board of Commissioners approved Contract
Modification No. 2 to extend the contract by 73 days due to weather and time delays associated
with cement stabilization; and
WHEREAS, on September 15, 2025, the Board of Commissioners approved
Contract Modification No. 3 in an amount not to exceed $3,000,000 with A&K Construction for
the construction of the Entry Plaza, for an updated contract price of $51,342,449.25; and
WHEREAS, on November 25, 2025, the Board of Commissioners approved
Contract Modification No. 4 with A&K Construction for a purchase credit in the amount of
$1,341,242.08 for items removed from the contract and direct purchased by the Fiscal Court, for
an updated contract amount of $50,001,207.17; and
WHEREAS, on January 13, 2026, the Board of Commissioners approved Contract
Modification No. 5 with A&K Construction in the amount of $1,055,383.75, for soil stabilization
for the sports park, making the updated contract amount $51,056,590.92; and
WHEREAS, Contract Modification No. 6 with A&K Construction was approved
by Municipal Order #3229, which reduced the contract amount by $119,800 for items removed
from the contract and directly purchased by the Fiscal Court, making the updated contract amount
$50,936,790.92. This modification was approved by the Fiscal Court on April 13, 2026; and
WHEREAS, Contract Modification No. 7 with A&K Construction will reduce the
contract amount by $476,506, for items removed from the contract and direct purchased by the
Fiscal Court, for an updated amount of $50,460,285.
NOW, THEREFORE, BE IT ORDERED BY THE BOARD OF
COMMISSIONERS OF THE CITY OF PADUCAH, KENTUCKY:
SECTION 1. The City Commission hereby approves Contract Modification
No. 7 reducing the contract with A&K by $476,506 for an updated contract sum of $50,460,285
and authorizes the Mayor to execute all documents related to same.
SECTION 2. This Order shall be in full force anA effect from and after the date
of its adoption. n
, A�
George Bray, Mayor
ATTEST:
bd�ay Parish, qfity Clerk
Adopted by the Board of Commissioners, August 11, 2026
Recorded by Lindsay Parish, City Clerk, August 11, 2026