HomeMy WebLinkAboutMO #3227MUNICIPAL ORDER NO. 3227
A MUNICIPAL ORDER APPROVING CHANGE ORDER 42 WITH JIM
SMITH CONTRACTING FOR ADDITIONAL SCOPE OF WORK FOR THE _
PADUCAH RIVERFRONT INFRASTRUCTURE IMPROVEMENT PROJECT
(BUILD) FOR $41,974, AND AUTHORIZING THE MAYOR TO EXECUTE
ALL DOCUMENTS RELATED TO SAME
WHEREAS, the City entered into a construction contract for the Paducah Riverfront
Infrastructure Improvements Project in the amount of $20,413,644.86, as approved by Municipal
Order No. 2985 on November 21, 2024; and
WHEREAS, Change Order #1 was approved by Municipal Order #3172 on January 14,
2026, and increased the contract by $273,093.03 to include electrical scope, bringing the
contract price to $20,686,737.90; and
WHEREAS, during the design and construction of the railing for the excursion pier, a
design change to add brackets to the landside railings was proposed. This change was
determined to improve the functionality and reduce maintenance for the railing and the pier.
The work totals are as follows:
Proposed Scope Cost
Revised guardrail brackets $39,975.24
JSC — 5% Overhead 1 998.76
Total Change Order #2 Amount $41,974.00
NOW, THEREFORE, BE IT ORDERED BY THE CITY OF PADUCAH, KENTUCKY:
SECTION 1. The Board of Commissioners approves Change Order #2 to the Paducah
Riverfront Infrastructure Improvement Project contract with Jim Smith Contracting Co., LLC in
the amount of $41,974, bringing the total contract price to $20,728,711.90, and authorizes the
Mayor to execute any documents related to same.
SECTION 2. The cost shall be paid from the BUILD Grant, Project Account Number
DT0050.
SECTION 3. This Order will be in full force and effect from and after the date of its
adoption.
^ATTEST:
Lindsay Pari h, City Clerk
Adopted by the Board of Commissioners, April 28, 2026
Recorded by Lindsay Parish, City Clerk, April 28, 2026
mo\Change Order #2 - Jim Smith Contracting — BUILD Grant Project
C&&
George Bray, May6Fr