HomeMy WebLinkAbout98-1-5801ORDINANCE NO. 98-1- S59'01
AN ORDINANCE AUTHORIZING AND DIRECTING THE MAYOR TO
EXECUTE CHANGE ORDER NO. 1 IN THE AMOUNT OF $17,886.93 WITH TILFORD
CONTRACTORS, INC. FOR THE PERKINS CREEK LIFT STATION
WHEREAS, the City approved Ordinance No. 96-7-5515 to enter into a contract
with Tilford Contractors, Inc., for the construction of the Perkins Creek Lift Station; and
WHEREAS, Change Order No. 1 is required for an increase in the amount of
$17,886.93 for miscellaneous work and materials and an increase of 86 days for the time of
completion to finalize the project for the above referenced contract, increasing the total contract
price to $964,748.93.
BE IT ORDAINED BY THE CITY OF PADUCAH, KENTUCKY:
SECTION 1. The Mayor is hereby authorized and directed to execute Change
Order No. 1 for an increase in the amount of $17,886.93 with Tilford Contractors, Inc., for
miscellaneous work and materials and an increase of 86 days for the time of completion required
to finalize the construction of the Perkins Creek Lift Station, increasing the total cost to
$964,748.93.
SECTION 2. This ordinance shall be read on two separate days and shall become
effective upon summary publication pursuant to KRS Chapter 424.
Mayor
ATTEST:
Introduced by the Board of Commissioners January 13, 1998
Adopted by the Board of Commissioners January 27, 1998
Recorded by Lenita Smith City Clem January 27, 1998
Published by The Paducah Sun,_ -7V,-, 3, I99
\winword\ordinanc\dees\chgord 1
394