HomeMy WebLinkAbout98-12-5985ORDINANCE NO. 98-12- IMM
AN ORDINANCE AUTHORIZING AND DIRECTING THE MAYOR TO
EXECUTE CHANGE ORDER NO. 1 IN THE AMOUNT OF $11,274.45 WITH TERRY
LAND DEVELOPMENT, INC., FOR THE LITTLEVILLE ROADWAY DRAINAGE AND
SEWER IMPROVEMENT PROJECT
WHEREAS, the City approved Ordinance No. 98-6-5866 to enter into a contract
with Terry Land Development, Inc., in the amount of $174,019.28 for the Littleville Roadway,
Drainage and Sewer Improvement Project; and
WHEREAS, Change Order No. 1 is required for an increase in the amount of
$11,274.45 for adjustment of actual quantities installed to finalize the project for the above
referenced contract, increasing the total contract price to $185,293.73.
BE IT ORDAINED BY THE CITY OF PADUCAH, KENTUCKY:
SECTION 1. The Mayor is hereby authorized and directed to execute Change
Order No. 1 for an increase in the amount of $11,274.45 with Terry Land Development, Inc., for
adjustment of actual quantities installed to finalize the project, increasing the total cost to
$185,293.73.
SECTION 2. Due to the requirement that the invoice be considered within a 30 -
day time period, an emergency is hereby declared to exist and this ordinance shall become
effective immediately with one reading.
a&4:1t-r
c'Mayor
ATTEST:
Lenita Smith, City Clerk
Introduced and adopted by the Board of Commissioners December 15, 1998
Recorded by Lenita Smith City Clerk, December 15, 1998
Published by The Paducah Sun, ��� /►� bR 23���1q 8
\winword\ordinanc\dees\chgord 1