HomeMy WebLinkAboutMO #2858MUNICIPAL ORDER NO. 2858
A MUNICIPAL ORDER ADOPTING CONTRACT MODIFICATION NO. 1 TO THE
CONSTRUCTION CONTRACT WITH VALLEY CONTRACTING SERVICES, LLC FOR
THE PROBATION & PAROLE OFFICE BUILDING CONSTRUCTION FOR AN INCREASE
IN THE AMOUNT OF $1,374.94, AND AUTHORIZING THE MAYOR TO EXECUTE THE
CHANGE ORDER
WHEREAS, by Municipal Order No. 2763, the City of Paducah authorized a
Construction Contract with Valley Contracting Services, LLC, in the amount of $111,400 construction
at the Probation & Parole Office Building; and
WHEREAS, during the construction contract it was discovered that additional labor was
necessary to complete the scope of work.
NOW, THEREFORE, BE IT ORDERED BY THE BOARD OF COMMISSIONERS OF
THE CITY OF PADUCAH, KENTUCKY:
SECTION 1. The City Commission hereby approves Change Order No. 1 to the
Construction Contract with Valley Contracting Services, LLC for a total price increase of
$1,374.94, and authorizes the Mayor to execute Change Order No. 1 on behalf of the City.
SECTION 2. The adoption of Change Order No. 1 increases the Contract
Amount by a total of $1,374.94, henceforth increasing the total agreement to an amount of
$112,774.94.
SECTION 3. This Order shall be in full force and fect from and after the date
of its adoption.
George Bray, Mayor
ATTEST:
(ix pa'�U_A�
indsay Parish, Kly
Clerk
Adopted by the Board of Commissioners, February 27, 2024
Recorded by Lindsay Parish, City Clerk, February 27, 2024
mo\change order 1 - Valley Contracting Services —Probation & Parole