HomeMy WebLinkAbout2023-08-8787ORDINANCE NO. 2023-08-8787
AN ORDINANCE AUTHORIZING AND DIRECTING THE MAYOR TO
EXECUTE CONTRACT MODIFICATION NO. 1 WITH JIM SMITH
CONTRACTING LLC. TO DECREASE THE CONTRACT BY $74,320 FOR THE
BUCKER LANE PROJECT
WHEREAS, On April 26, 2022, the City approved Ordinance 2022-04-8730,
authorizing a professional services contract with Jim Smith Contracting LLC for a construction
contract in the amount of $1,985,514.37 for the Bucker Lane Project; and
WHEREAS, it is now necessary to modify the contract due to the fact that cost
savings during construction resulted in savings of $74,320; and
WHEREAS, Contract Modification No. 1 is required to decrease the contract amount
by $74,320, adjusting the total construction project from $1,985,514.37 to $1,911,194.37.
KENTUCKY:
NOW, THEREFORE, BE IT ORDAINED BY THE CITY OF PADUCAH,
SECTION 1. The Mayor is hereby authorized to execute Contract Modification No.
1 with Jim Smith Contracting LLC for a decrease in the amount of $74,320 and a new total contract
cost of $1,911,194.37.
SECTION 2. This ordinance shall be readwo separate days and will become
effective upon summary publication pursuant to
Bray, Mayor
ATTEST:
Lindsay Parish, (@ C erk
Introduced by the Board of Commissioners July 25, 2023
Adopted by the Board of Commissioners, August 8, 2023
Recorded by Lindsay Parish, City Clerk, August 8, 2023
Published by The Paducah Sun, August 11, 2023
\ord\eng\CHGORDI — Jim Smith Contracting — Buckner Lane Project