ORDINANCE NO. 2003-8-6685
AN ORDINANCE AUTHORIZING AND DIRECTING THE MAYOR TO
EXECUTE CHANGE ORDER NO. 1 WITH FLORENCE & HUTCHESON, INC, FOR THE
PECAN DRIVE ROADWAY DESIGN PROJECT
WHEREAS, the City approved Ordinance No. 2002-10-6584 to enter into a
contract with Florence & Hutcheson, Inc. in the amount of $295,279.00 for the Pecan Drive
Roadway Design Project; and
WHEREAS, Change Order No. 1 is required for an increase in the amount of
$17,800.00 for required additional environmental studies to be performed at Perkins and Crooked
Creek bridge crossings, in order to finalize the project for the above referenced contract,
increasing the total contract price to $313,079.00.
BE IT ORDAINED BY THE CITY OF PADUCAH, KENTUCKY:
SECTION 1. The Mayor is hereby authorized and directed to execute Change
Order No. 1 for an increase in the amount of $17,800.00 with Florence & Hutcheson, Inc., for
required additional environmental studies to be performed at Perkins and Crooked Creek bridge
crossings in order to finalize the project, increasing the total cost to $313,079.00.
SECTION 2. This shall be charged to the Pecan Drive Roadway Design account
(ST0018).
SECTION 3. This ordinance shall be read on two separate days and will become
effective upon summary publication pursuant to KRS Chapter 424.
ATTEST:
I
Tammara S. Brock, City Clerk
Introduced by the Board of Commissioners August 12, 2003
Adopted by the Board of Commissioners August 26, 2003
Recorded by Tammara S. Brock, City Clerk, August 26, 2003
Published by The Paducah Sun, September 3, 2003
\ord\eng\chgordl- Pecan Drive Roadway Design Project