HomeMy WebLinkAbout2003-12-6736624
ORDINANCE NO. 2003-12-6736
AN ORDINANCE AUTHORIZING AND DIRECTING THE MAYOR TO
EXECUTE CHANGE ORDER NO. 2 WITH FLORENCE & HUTCHESON, INC., FOR THE
PECAN DRIVE BRIDGE CONSTRUCTION PROJECT
WHEREAS, the City approved Ordinance No. 2002-10-6584 to enter into a
contract with Florence & Hutcheson, Inc. in the amount of $295,279.00 for the Pecan Drive
Bridge Construction Project; and
WHEREAS, Change Order No. 1 was required for an increase in the amount of
$17,800.00 for required additional environmental studies that were performed at Perkins Creek
and Crooked Creek bridge crossings, increasing the total contract price to $313,079.00; and
WHEREAS, Change Order No. 2 is required for an increase in an amount not to
exceed $21,500.00 for construction observation services of the Pecan Drive Bridge and to
finalize the project for the above referenced contract, the total contract price will increase to
$334,579.00.
BE IT ORDAINED BY THE CITY OF PADUCAH, KENTUCKY:
SECTION 1. The Mayor is hereby authorized and directed to execute Change
Order No. 2 for an increase in the amount of $21,500.00 with Florence & Hutcheson, Inc., for
construction observation services of the Pecan Drive Bridge and to finalize the project,
increasing the total cost to $334,579.00.
(ST0022).
SECTION 2. This shall be charged to project account Pecan Roadway Design Act
SECTION 3. This ordinance shall be read on two separate days and will become
effective upon summary publication pursuant to KRS Chapter 424.
ATTEST:
Tammara S. Brock, City Clerk
Introduced by the Board of Commissioners November 25, 2003
Adopted by the Board of Commissioners December 9, 2003
Recorded by Tammara S. Brock, City Clerk, December 9, 2003
Published by The Paducah Sun, December 16, 2003
\ord\eng\chgord2- Pecan Drive Bridge