Comprehensive Stormwater Master Plan Update - Recommendation of Stormwater Impact Fee
Principal-In-Charge/Senior Planning Advisor John Lyons with Strand Associates provided an update to the Paducah Board of
Commissioners on the work completed in partnership with the City of Paducah and BFW Engineering & Testing on the
second phase of the Comprehensive Stormwater Master Plan.
The Plan’s second phase addresses the creation of a Stormwater Utility with an associated Stormwater Impact Fee. The
proposed fee is a revenue stream that would be used to fund items such as capital improvement drainage projects, operations
and maintenance of the existing infrastructure, the City’s flood protection system (floodwall), regulatory compliance
requirements, infrastructure repair and replacement, and the administration of the program through staffing and equipment.
Lyons explained that a stormwater utility most often uses an Equivalent Residential Unit (ERU) as a funding mechanism. The
ERU is based on the impervious surface on a parcel such as rooftops, driveways, and patios. Strand sampled 50 residential
parcels in Paducah to determine an average amount of impervious area. The average is 3500 square feet per residential parcel
which would equal one ERU. It would be proposed for each residential parcel to pay the same amount per month, one ERU.
Lyons proposes the monthly cost per ERU to be $6.13. The proposed fee could generate $2.7 million annually which would
be dedicated to stormwater programs, projects, administration, and maintenance. Please note that this is a recommended
rate. The Paducah Board of Commissioners has not approved this rate and would like to have additional
information about how the rate would impact various businesses, schools, and other entities.
Non-residential parcels such as commercial entities would pay a monthly fee equal to the total amount of impervious area on
the property divided by 3500 and then multiplied by the proposed monthly rate. The City also could look into developing a
credit policy for non-residential property owners that exceeded local stormwater detention and water quality requirements.
Strand will be providing the City with the calculated impervious area for each non-residential parcel in Paducah. Stay tuned
for details on how individual businesses or non-residential entities will be able to get information regarding the amount of
impervious area on their property in order to make total fee calculations.
There are approximately 1500 stormwater utilities in the United States with about a dozen of them in Kentucky. In
Kentucky, the fees for residential parcels range from $1.50 per month in Murray to $9.90 per month in Louisville. The
national average is $5.34 per month.
Paducah’s proposed Stormwater Impact Fee includes covering the costs associated with the floodwall which currently are
funded through the City’s General Fund. If the floodwall costs remained in the General Fund and were not included as part
of the Stormwater Utility, the proposed monthly fee for residential parcels (1 ERU) would be $4.44.
As a reminder, the first phase of the Comprehensive Stormwater Master Plan has been completed. The first phase used the
July 7, 2015, storm event to create a model of Paducah’s natural and manmade infrastructure including storm and combined
sewer systems, topography, drainage basins, and river systems. This computer model along with community input was used to
determine flood-prone areas in Paducah. The first phase identified more than $43 million in flood mitigation projects located
within ten priority areas. If the drainage projects outlined in the ten project areas were completed, 245 homes in the City
would not be flooded with an additional 289 structures seeing a reduction in flooding.
City of Paducah Strategic Action Plan Update
The Paducah Board of Commissioners approved a municipal order to update the City of Paducah Strategic Plan Action Steps
and the Vision Statement. The Board and City Manager’s Office participated in a retreat earlier this year on January 5 to
review the Plan’s elements. The Board decided to revise the Vision Statement to add the phrase healthy lifestyle. The updated
Vision Statement is as follows: Paducah is a city where people strive to reach their full potential through lifelong learning, healthy lifestyle,
creativity, culture and compassion for one another.
Pam Spencer, Public Information Officer
City of Paducah P.O. Box 2267 Paducah, Kentucky 42002
270/444-8669 Office 270/443-5058 Fax
Website: http://paducahky.gov Email: pspencer@paducahky.gov
The Board also updated the Key Performance Indicators and the Action Items under each Indicator and their priority levels.
In the plan, the highest priorities are known as WIN (What's Important Now) initiatives. The key team member assigned to
each WIN will be responsible for providing monthly updates. Updates for the other strategic plan initiatives will be reported
twice a year.
In a separate action, the Board introduced an ordinance for a contract with Innovations Branding House (vote February 26)
for community engagement initiatives regarding the Strategic Plan including print materials, social media content, a website,
and videos. After the initial launch of Our Paducah, Innovations Branding House will lead quarterly campaigns related to
specific plan elements. The cost of the initial launch is $20,000 for the current fiscal year with a cost of $36,000 during the
next fiscal year for the quarterly campaigns.
Quick Highlights
Boards and Commissions:
o Jeff Holland reappointed to the Paducah-McCracken County Riverport Authority.
o William Baxter reappointed to the Board of Adjustment.
Municipal Order approved to transfer funds totaling $20,000 from the Commission Reserve Account to the Mayor
and Commissioners’ Promotions Account for the Innovations Branding House Contract.
Municipal Order approved accepting the purchase of bomb suits, helmets, and bomb suit repair kits for a total
purchase cost of $49,499 through the U.S. General Services Administration Cooperative Purchasing Program. A
Homeland Security Grant Award will cover the cost of the purchases. No local match is required.
Ordinance approved to close the unnamed right-of-way between Buckner Lane and Exall Lane as requested by the
adjacent property owners.
Ordinance approved to execute the final plat of subdivision and the escrow agreement for Townhomes of LaBarri
Farms Subdivision. This property is located at 1720 and 1740 New Holt Road.
###