HomeMy WebLinkAbout2021-07-8694ORDINANCE NO. 2021-07-8694
AN ORDINANCE AUTHORIZING AND DIRECTING THE MAYOR TO
EXECUTE CHANGE ORDER NO. 1 WITH PACE CONTRACTING LLC. TO INCREASE
THE CONTRACT BY $121,733.29 FOR THE PUMP STATION #2 REHABILITATION
PROJECT
WHEREAS, On August 25, 2020, the City approved Ordinance 2020-08-8652,
authorizing a professional services contract with Pace Contracting, LLC for a construction
contract in the amount of $4,500,000 for the Pump Station #2 Rehabilitation Project; and
WHEREAS, unforeseen circumstances including missing components, damaged
materials, fabrication of Motor #5 adjustment nut, and emergency repairs of the 48" discharge
pipe have resulted in additional costs to Pace Contracting; and
WHEREAS, Change Order No. 1 is required for an increase in the amount of
$121,733.29 adjusting the total construction project from $4,500,000 to $4,621,733.29.
KENTUCKY:
NOW, THEREFORE, BE IT ORDAINED BY THE CITY OF PADUCAH,
SECTION 1. The Mayor is hereby authorized to execute Change Order No. 1
with Pace Contracting, LLC for an increase in the amount of $121,733.29 and a new total
contract cost of $4,621,733.29.
SECTION 2. This expenditure shall be charged to the Pump Station 42 Project
Account FW0014.
SECTION 3. This ordinance shall be
effective upon summary publication pursuant
ATTEST:
EAJ�
Lindsay Parish, Cit, Clerk
0.
two separate days and will become
424.
Bray, Mayor
Introduced by the Board of Commissioners July 13, 2021
Adopted by the Board of Commissioners, July 27, 2021
Recorded by Lindsay Parish, City Clerk, July 27, 2021
Published by The Paducah Sun July 30, 2021
\ord\eng\CHGORDI- Pace Contracting LLC — Pump Station #2