A RESOLUTION APPROVING THE TIMETABLE OF THE PROPOSED SEWER
IMPROVEMENT PROGRAM FOR THE CITY OF PADUCAH, KENTUCKY, AS PREPARED
AND SUBMITTED ON DECEMBER 16, 1961BY BURNS AND McDONNELL, CONSULTING
ENGINEERS OF KANSAS CITY, MISSOURI
WHEREAS the City of Paducah, Kentucky and the Officials thereof,
recognize the fact that a problem exists in the overloading of the
present combined sewer system, and
WHEREAS, on December 8, 196h, the Board of Commissioners of the
City of Paducah, Kentucky, adopted a resolution authorizing Borns &
McDonnell, Consulting Engineers of Kansas City, Missouri, to inves-
tigate and report to the Board of Commissioners as to certain matters
pertaining to the sewer improvement program of the -City., and
WHEREAS, pursuant thereto, said Burns & McDonnell on December 16th
submitted a timetable for the proposed sewer improvement program of.said
city, and
WHEREAS, the Board of Commissioners of said city desires to officiall,
approve said timetable.
NOW THEREFORE, BE IT RESOLVED BY THE BOARD OF COMMISSIONERS OF THE
CITY OF PADUCAH, KENTUCKY:
SECTION 1. That.the timetable of the proposed sewer improvement
program for the City of.Paducah, Kentucky, prepared and submitted to the
Citv on.December 16, 196h, be, and the same is hereby, approved, said
timetable being in words and figures.as follows:
"PADUCAH, KENTUCKY
PROPOSED SEWER IMPROVEMENT PROGRAM
TIMETABLE
1. Complete report to theCity as outlined
January 18,
1965
in Section 1 of December t, 196L resolution
2. *Bond consultants complete review of report and
February
15, 1965
prepare ordinance for revenue bonds for
minimum program
3. City passes ordinance and publishes it is newspaper
March 1,
1965
Engineers authorized to commence design on relief
MArch 1,
1965
and sanitary sewers
h. First contract for relief sewers ready for bidding
September
1, 1965
5. Take bids and then commence construction on
October 1,
1965
Contract 1
5. Second contract -relief sewers
November
1, 1965
Third contract -sanitary sewers ready for bidding.
November
1, 1965
7. General obligation bond issue to voters
November
2, 1965
.(Minimum ultimate program)
8. Take bids and commence construction
December
1, 1965
on Contracts 2 and 3
9. Fourth contract - sanitary sewers ready for bidding January 1, 1966
10. Engineers authorized to proceed on design for January 1, 1966
ultimate sewer propram if approved by voters
*Ordinance to contain clause to submit minimum ultimate program to
voters in November, 1965 as an issue of General Obligation Bonds for
Storm and relief sewers. Ordinance to also set connection charge for
sanitary -sewer program."
446
SECTION 2. That it is the intent and purpose of said Board of
Commissioners to do everything within its power to accelerate and speed
up each and every phase of the timetable set out in Section 1 hereof.
SECTION 3. That the total and entire sewer proa_ram will be
carried throuph by the Board of Commissioners of the City as
expeditiously as possible.
SECTION 4. This resolution shall be in full force and effect
from and after its adoption. .
Mayor'
Passed by the Board of Commissioners December 22, 1964
Recorded by Sarah Thurman, City Clerk, December 22, 1964.