HomeMy WebLinkAbout2021-01-8668ORDINANCE NO. 2021-01-8668
AN ORDINANCE AUTHORIZING AND DIRECTING THE MAYOR TO
EXECUTE CHANGE ORDER NO. 1 WITH JIM SMITH CONTRACTING, LLC, TO
INCREASE THE CONTRACT BY $37,585.10 FOR THE GREENWAY TRAIL PHASE V
PROJECT
WHEREAS, On April 14, 2020, the City approved Ordinance 2020-04-8631,
authorizing a construction contract with Jim Smith Contracting, LLC, for $479,350.50 to
construct the Greenway Trail Phase V; and
WHEREAS, during construction of the project, large concrete deposits required
field adjustments to the project. The entire project was raised 1'0" to 1'6" in the vertical plane to
avoid the concrete. This adjustment resulted in importing soil to provide backfill and planting
areas for landscaping in the project area. Line items change orders resulted in ($65,846.32) and
$103,431.42 for a net change of $37,585.10; and
WHEREAS, Change Order No. 1 is required for an increase in the amount of
$37,585.10 adjusting the total construction project from $479,350.50 to $516,935.60.
BE IT ORDAINED BY THE CITY OF PADUCAH, KENTUCKY:
SECTION 1. The Mayor is hereby authorized to execute Change Order No. 1 for
an increase in the amount of $37,585.10 with Jim Smith Contracting, LLC, for a total contract
cost of $516,935.60.
SECTION 2. This expenditure shall be charged to the Greenway Trail Phase V
Project Account PA0111.
SECTION 3. This ordinance shall be read on two separate days and will become
effective upon summary publication pursuant to KRS Chapter 424.
ATTEST:
Lindsay Parish, ity Clerk
Introduced by the Board of Commissioners December 15, 2020
Adopted by the Board of Commissioners, January 12, 2021
Recorded by Lindsay Parish, City Clerk, January 12, 2021
Published by The Paducah Sun January 15, 2021