HomeMy WebLinkAbout2005-11-7041ORDINANCE 2005-11-7041
AN ORDINANCE AUTHORIZING AND DIRECTING THE MAYOR TO
EXECUTE CHANGE ORDER NO.4 WITH FLORENCE & HUTCHESON, INC., FOR
THE PECAN DRIVE/BUCKNER LANE ROADWAY PROJECT
WHEREAS, the City adopted Ordinance No. 2005-4-6951 authorizing the
Mayor to execute Change Order #3 with Florence & Hutcheson, Inc., for additional
surveying and design work in an amount not to exceed $61,024.00, thereby increasing the
contract amount to $395,603.00; and
WHEREAS, all work for additional surveying and design has now been
completed with the total amount of $392,174.50 paid to date; and
WHEREAS, Change Order No. 4 is required as a decrease in the amount of
$3,428.50, in order to finalize the total project cost for the above referenced contract to
$392,174.50.
BE IT ORDAINED BY THE CITY OF PADUCAH, KENTUCKY:
SECTION 1. The Mayor is hereby authorized and directed to execute Change
Order No. 4 for an overall price reduction in the amount of $3,428.50 for the City of
Paducah's Pecan Drive/Buckner Lane Roadway Project, decreasing the total contract price to
$392,174.50.
SECTION 2. This ordinance shall be read on two separate days and will
become effective upon summary publication pursuar
ATTEST:
Tammara S. Brock, City Clerk
Introduced by the Board of Commissioners, November 8, 2005
Adopted by the Board of Commissioners, November 22, 2005
Recorded by Tammara S. Brock, City Clerk, November 22, 2005
Published by The Paducah Sun, November 30, 2005