HomeMy WebLinkAbout2005-8-7002ORDINANCE 2005-8-7002
AN ORDINANCE AUTHORIZING AND DIRECTING THE MAYOR TO
EXECUTE CHANGE ORDER 1 WITH H & G CONSTRUCTION, INC., FOR THE
PECAN DRIVEBUCKNER LANE BRIDGE CONSTRUCTION PROJECT
WHEREAS, the City approved Ordinance No. 2003-10-6703 to enter into a
contract with H & G Construction, Inc., in the amount of $883,956.10.00 for construction of
the related bridges over Perkins Creek and Crooked Creek for the Pecan Drive/Buckner Lane
Bridge Construction Project; and
WHEREAS, Change Order No. 1 is required as a decrease in the amount of
$2,768.57, in order to finalize the total project cost for the above referenced contract to
$881,187.53.
BE IT ORDAINED BY THE CITY OF PADUCAH, KENTUCKY:
SECTION 1. The Mayor is hereby authorized and directed to execute Change
Order 1 for an overall price reduction in the amount of $2,768.57 for the City of Paducah's
Pecan Drive/ Buckner Lane Bridge Construction Project, decreasing the total contract price
to $881,187.53.
SECTION 2. This ordinance shall be read on two separate days and will
become effective upon summary publication pursuant to KRS Chapter 424.
ATTEST:
4nm*k
Introduced by the Board of Commissioners July 26, 2005
Adopted by the Board of Commissioners, August 9, 2005
Recorded by Tammara S. Brock, City Clerk, August 9, 2005
Published by The Paducah Sun, August 17, 2005
\ord\eng\chgord 1 -Pecan Dr -Buckner Ln Bridge