HomeMy WebLinkAboutMO #2187MUNICIPAL ORDER NO. 2187
A MUNICIPAL ORDER APPROVING CHANGE ORDER NO. 1 WITH
HUFFMAN CONSTRUCTION, LLC, FOR A CONTRACT REDUCTION IN THE
AMOUNT OF $25,000 FOR THE FLOODWALL PUMP STATION #2
REHABILITATION PROJECT, AND AUTHORIZING THE MAYOR TO EXECUTE THE
CHANGE ORDER
WHEREAS, the City approved Ordinance No. 2018-4-8523 on April 10,
2018, to enter into a contract with Huffman Construction, LLC, in the amount of $4,947,000
for the Floodwall Pump Station #2 Rehabilitation Project; and
WHEREAS, a change in removal techniques implemented for pumps 4,5, and
6, has resulted in a decrease to the total price of the contract; and
WHEREAS, the City of Paducah now desires to approve Change Order No. 1
to decrease the contract with Huffman Construction, LLC, by $25,000.
NOW, THEREFORE, BE IT ORDERED BY BOARD OF
COMMISSIONERS OF THE CITY OF PADUCAH, KENTUCKY:
SECTION 1. The City hereby approves Change Order No. 1 with Huffman
Construction, LLC, for a price decrease in the amount of $25,000 for the City of Paducah's
Floodwall Pump Station Rehabilitation Project, henceforth reducing the total contract amount
to $4,922,000.
SECTION 2. The City hereby authorizes the Mayor to execute Change Order
No. 1, as authorized in Section 1 above.
SECTION 3. This Order shall be in full force and effect from and after the
date of its adoption.
J�
Brandi Harless, Mayor
ATTEST:
mdsay Parish, Cita✓Clerlc
Adopted by the Board of Commissioners, November 27, 2018
Recorded by Lindsay Parish, City Clerk, November 27, 2018