HomeMy WebLinkAbout2018-04-8523ORDINANCE NO. 2018-4-8523
AN ORDINANCE ACCEPTING THE BID OF HUFFMAN CONSTRUCTION,
LLC, FOR THE FLOODWALL PUMP STATION #2 REHABILITATION PROJECT, AND
AUTHORIZING THE MAYOR TO EXECUTE A CONTRACT FOR SAME
WHEREAS, the City requested sealed competitive bids for the Floodwall Pump
Station No. 2 Rehabilitation which is a component of the larger Floodwall Rehabilitation Project,
currently in progress; and
WHEREAS, the bid of Huffman Construction, LLC, a Kentucky limited liability
Company, dated February 23, 2018, in the amount of $4,947,000.00 for the Floodwall Pump
Station No. 2 Rehabilitation is in substantial compliance with the bid specifications; and
WHEREAS, Design Engineer of Record, HDR Engineering, and City staff are
recommending that the bid be awarded and the contract be entered into with Huffman
Construction, LLC.
KENTUCKY:
NOW, THEREFORE, BE IT ORDAINED BY THE CITY OF PADUCAH,
SECTION 1. That the City of Paducah accepts the bid of Huffman Construction,
LLC, in the amount of $4,947,000.00, for construction services for the Floodwall Pump Station
No. 2 Rehabilitation, said bid being in substantial compliance with the bid specifications, and as
contained in the bid of Huffman Construction, LLC, dated February 23, 2018.
SECTION 2. That the Mayor is hereby authorized to execute a contract with
Huffinan Construction for the Floodwall Pump Station No. 2 Rehabilitation, authorized in
Section 1 above, according to the specifications, bid proposal and all contract documents
heretofore approved and incorporated in the bid and authorizing the Mayor to execute all other
documents associated with the contract.
SECTION 3. This expenditure shall be charged to project account FW0014.
SECTION 4. This ordinance shall be read on two separate days and will become
effective upon summary publication pursuant to KRS Chapter 424.
ATTEST:
Tammara S. Sanderson, City Clerk
Mayor
Introduced by the Board of Commissioners, March 27, 2018
Adopted by the Board of Commissioners, April 10, 2018
Recorded by Tammara S. Sanderson, City Clerk, April 10, 2018