HomeMy WebLinkAbout2017-09-8497ORDINANCE 2017-9-8497
AN ORDINANCE AUTHORIZING THE MAYOR TO EXECUTE
CHANGE ORDER NO. 1 FOR THE NOBLE PARK LAKE BANK STABILIZATION
PROJECT—PHASE II
WHEREAS, the City approved Ordinance No. 2017-2-8477 to enter into a
contract with Youngblood Excavating & Contracting, LLC., in the amount of $242,980.00
for the construction of the Noble Park Lake Bank Stabilization Project –Phase II; and
WHEREAS, Change Order No. 1 in the amount of $20,500 is necessary to
pay for tree removal which interfered with construction, removal of organic materials from
pond, a new pedestrian bridge connecting land between shelters and playground on the east
side of the park, and to extend the contract until September 30, 2017. Therefore, changing
the total contract amount to $263,480.00.
BE IT ORDAINED BY THE CITY OF PADUCAH, KENTUCKY:
SECTION 1. The Mayor is hereby authorized to execute Change Order No. 1
in the amount of $20,500 with Youngblood Excavating & Contracting, LLC, for additional
items that are in excess of the original contract for the Noble Park Lake Bank Stabilization
Project—Phase II, this will change the original total contract amount to $263,480.00. This
change order also extends the contract time of completion to September 30, 2017.
SECTION 2. This expenditure shall be charged to the Noble Park Bank
Stabilization Phase II account, project number PA0107.
SECTION 3. This ordinance shall be read on two separate days and will
become effective upon summary publication pursuant to KRS Chapter 424.
Mayor
ATTEST:
Tammara S. Sanderson, City Clerk
Introduced by the Board of Commissioners, August 22, 2017
Adopted by the Board of Commissioners, September 12, 2017
Recorded by Tammara S. Sanderson, City Clerk, September 12, 2017
Published by The Paducah Sun, September 15, 2017