HomeMy WebLinkAbout2010-11-7755ORDINANCE 2010-11-7755
AN ORDINANCE AUTHORIZING THE MAYOR TO EXECUTE CHANGE
ORDER NO. 1 WITH CENTRAL PAVING COMPANY OF PADUCAH, FOR THE NOBLE
PARK PARKING LOT RECONSTRUCTION PROJECT
WHEREAS, the City approved Ordinance No. 2010-6-7685 to enter into a
contract with Central Paving Company of Paducah, in the amount of $463,000, for the Noble
Park Parking Lot Reconstruction Project; and
WHEREAS, due to unforeseen circumstances, additional expenses have occurred
due to poor soil conditions and an unmarked water line; and
WHEREAS, Change Order No. 1 is required as an increase in the amount of
$69,386.23, thereby increasing the total project cost for the above referenced contract to
$532,386.23; and
WHEREAS, due to this additional work, the time for completion of the original
contract has been extended by seventeen (17) days to November 5, 2010.
BE IT ORDAINED BY THE CITY OF PADUCAH, KENTUCKY:
SECTION 1. The Mayor is hereby authorized to execute Change Order No. 1
with Central Paving Company of Paducah for the Noble Park Parking Lot Reconstruction
Project, in the amount of $69,386.23, increasing the total contract price to $532,386.23 and
extending the original contract by seventeen (17) days to November 5, 2010.
SECTION 2. This ordinance shall be read on two separate days and will become
effective upon summary publication pursuant to KRS Chapter 424.
ATTEST:
jarr�ah_�S' 610c*
Tammara S. Brock, City Clerk
Introduced by the Board of Commissioners, October 26, 2010
Adopted by the Board of Commissioners, November 9, 2010
Recorded by Tammara S. Brock, City Clerk, November 9, 2010
Published by The Paducah Sun, November 16, 2010
\ord\eng\chgord 1 -Noble Park Parking Lot Reconstruction Proj